๐Ÿ“‹ SAP PS โ€“ Project System Transaction Codes

Full reference for SAP Project System (PS) transaction codes covering project definition, WBS structure, network activities, project budgeting, cost planning, settlement, and reporting.

Module: PSSub-Modules: WBS ยท Networks ยท Budgeting ยท ReportingT-Codes: 35+SAP Release: ECC & S/4HANA

Project Structure โ€“ WBS & Project Builder

T-CodeTransaction NameDescription & Usage ScenarioType
CJ20NProject BuilderComprehensive graphical tool for creating and maintaining entire project structures: WBS, networks, activities.
Primary PS transaction for project managers. Create and maintain all project elements in one screen.
โ˜… Common
CJ01Create Work Breakdown StructureCreate WBS (Work Breakdown Structure) elements defining the project hierarchy and cost collection points.
Used to set up project cost structure before planning or committing costs.
โ—‰ Master Data
CJ02Change WBS ElementModify WBS element: description, responsible person, status, system status, or billing element flag.
Used during project execution to update project details and control project status changes.
CJ03Display WBS ElementView WBS element master data and status without modification.
Used for project reference, audit, and status review by project stakeholders.
CN01Create Network (Standard)Create a project network for detailed activity scheduling with dependencies and resources.
Used for complex projects where activity sequencing, resource planning, and schedule optimization are required.
CN21Create Project (Combined)Create a complete project including project definition, WBS elements, and network in one flow.
Used in project creation workflows where all project elements are set up simultaneously at kickoff.
Advertisement

Project Budgeting & Planning

T-CodeTransaction NameDescription & Usage ScenarioType
CJ40Change Project Plan (Costs)Enter or update project cost plan values for WBS elements by fiscal year and period.
Used during project planning and re-planning cycles to establish cost baselines by WBS element.
โ˜… Common
CJ30Display Original BudgetView the original approved budget for a project or WBS element as first released.
Used as reference for budget performance management. Compare against current availability.
โ–ฒ Report
CJ31Change Original BudgetEnter the initial approved project budget for WBS elements.
Used by project controllers to load the approved project budget before project execution begins.
CJ32Release Project BudgetRelease the original budget to make funds available for commitments and spending.
Budget must be released before purchase orders or other cost commitments can be created against WBS.
โ˜… Common
CJ3BSupplement BudgetIncrease an existing project budget when approved scope or cost changes require additional funds.
Used for budget revisions when project scope changes are formally approved.
CJ38Return BudgetReturn unused budget from WBS elements, reducing the available budget balance.
Used at project close-out or when scope is reduced to release uncommitted budget back to the pool.

Project Execution & Cost Management

T-CodeTransaction NameDescription & Usage ScenarioType
CJ8GSettle Project Costs (Mass)Settle actual costs from multiple WBS elements to receiver objects (G/L accounts, cost centers, assets).
Run at period-end and project completion to transfer capitalized costs to fixed assets or expense accounts.
โ˜… Common
CJI3Project Actual Cost Line ItemsDisplay actual cost line items posted to project WBS elements or network activities.
Used for project cost analysis, expense verification, and budget consumption tracking.
โ˜… Common
CN41Project Information SystemCentral reporting hub for all project system reports: costs, revenues, budgets, schedules.
Used by project managers and controllers for comprehensive project performance analysis.
โ–ฒ Report
S_ALR_87013532Plan/Actual Comparison (Projects)Standard report comparing planned vs actual costs for projects with period-level detail.
Core PS report for project performance management and earned value analysis.
โ–ฒ Report
CJ20Project OverviewDisplay an overview of all active projects with status, budget, and cost information.
Used by portfolio managers to review project status across the entire project landscape.
โ–ฒ Report
CJ06Display Project DefinitionView top-level project definition attributes including project type, responsible CC, and dates.
Used for project reference and status overview at the top level.